Case Studies

Filed under: Private client

Cotswold Barn Conversion & Extension

Type: Conversion & Extension
Location: Gloucestershire
Build Cost: £750,000
Form of Contract: JCT Intermediate Building Contract 2005 With Contractors Design
Completion: May 2015

Demolition of the existing goods shed and subsequent Alterations and Extension to the existing Barn to form holiday unit / living accommodation together with drainage and associated landscaping / external works to immediate surroundings.









More info
View all Private client
case studies

Filed under: Registered Social Landlord

4 Affordable New Build Flats, Coleford - £375k

Description: Refurbishment & Alterations of 18th century School Buildings and Conversion into compliant Healthcare Facilities, including external works, new drainage system, new M&E installations & internal finishes
Location: Coleford, Gloucestershire
Build Cost: £375,000
Type: New Build
Form of Contract: JCT Design & Build Contract 2011

Programme

On Site:  July 2014 – February 2015

Pre-Contract Services

  • Preparation of works cost Budget and Cost Plan
  • Value Engineering & Budget Risk Management
  • Schedule of Works preparation
  • Tender Preparation – Single Stage
  • Review & Analytical Reporting on Tenders received
  • Preparation of Contract Documents
  • Cashflow forecasting
  • CDM Coordinator Role

Post-Contract Services

  • Cost Management of construction works
  • CDM Coordinator Role
  • Risk Management & Client Design Team support
  • Recording of Works
  • Interim Valuation of Works
  • Cost Reporting to Client & Final Account Forecasting
  • Cost Management of Variations
  • Cashflow Management
  • Final Account Agreement
More info
View all Registered Social Landlord
case studies

Filed under: Main Contractors

M&S Kensington Concept - £1.4m

Type: FastTrack Retail Fit Out & Refurb
Location: Kensington, London
Build Cost: £1,400,000
Form of Contract: M&S Standard Design & Construct Contract

More info
View all Main Contractors
case studies

Filed under: Public Bodies

Refurbishment of Health Centre - £550k

 

Description: Refurbishment & Alterations of 18th century School Buildings and Conversion into compliant Healthcare Facilities, including external works, new drainage system, new M&E installations & internal finishes
Location: Health Centre, Cheltenham
Build Cost: £550,000
Form of Contract: NEC3 Option A: Priced Contract with Activity Schedule

Programme

Pre-Contract: Nov 2014
Tender: Dec 2014
On site: Jan 2015 - April 2015

Pre-Contract Services

  • Preparation of Outline Budget and Cost Plan
  • Schedule of Works preparation
  • User Group & Stakeholder Liaison
  • Tender Preparation
  • Preparation of Contract
  • Review & Analytical Reporting on Tenders received
  • CDM - Pre-construction Information

Post-Contract Services

  • Cost Management of construction works
  • Risk Management & Client, Design Team support
  • Recording of Works
  • Interim Valuation of Works
  • Cost Reporting to Client & Final Account Forecasting
  • Cost Management of Variations
  • Cashflow Management
  • Final Account Agreement
  • Clerk of Works
  • CDM - Review of Contractors H&S Plan & On-site Monitoring
More info
View all Public Bodies
case studies